Utility Layout Plan Comments
Here are the comments and questions from our initial review, completed on Sat Jan 17, 2015
1.FRONT ENTRY/FOYER
Here are the comments and questions from our initial review, completed on Sat Jan 17, 2015
1.FRONT ENTRY/FOYER
Per David Crompton we will need to convert all our sheets to 24x36 for our Construction Documents. I've just added G0.1-G0.5 to the project pages.
Read more…Following is a summary of our meeting today with Mitch and Jim over the outstanding items related to civil and soils engineering:
Below is a copy of a Previous E-mail Response from David:
David Crompton
Principal Planner
Planning Division
Town of Danville
Tel: 925.314.3349
From: Tim Haley [mailto:impluvium@gmail.com]
Sent: Wednesday, April 02, 2014 2:32 PM
To: David Crompto
Added A6.1 - Ceiling Plan for your review Prior to our Meeting on Tuesday. I should be able to post A6.2 - Electrical Plan on Monday. (Add any comments as a reply to this forum thread) - Thanks.
Read more…HI-
Please find attached my latest hardscape layout plan for you to review. I have also included a typical elevation for the entry gate. You do not have to use this look as you can always go to a gate designer who specificaly do scul
Read more…We had our first team meeting with Mike and Ross to go over landscape design and some things we need from Mike for the next meeting. With the schematic design wrapping up for the Landscape Design we will be scheduling the next meeting next Friday an
Read more…After our team meeting on Friday August 1, Tim asked us to post the photos of the home exterior we liked. This will be used for the color board for submitting the plans to the town.
In general, we want to stay to a more earthy color scheme. We prefer
Read more…This discussion is to document our efforts in meeting with various Lawrence road neighbors in regards to the build project.
1. 8/31/14 - Met with Susan and Mark Tu to share the house project plans that were submitted to the town. They were very sup
Read more…Just spoke with Mike and he is going to check with the Town of Danville when the cut off is for grading (in Contra Costa County it is in October but Danville will be different). He will then post a "proposed" construction schedule based on this. Ho
Read more…1. Mud Room - We would like the window on the East side to be higher (privacy concerns)
2. Bed room #3- We would like the two small clerestory windows to be removed. It looks odd above the big window panels. One alternative is to lower the entire cei
Read more…Submitted by Liwen Cheung on March 26,2014 Vince showed me the drawing that you guys looked over on Wednesday. I like the concept to allow light into each room. It's a new look to get used to for sure as I am used to rectangular and boxy homes. We h
Read more…